Slab Remediation At
Sydney Airport

Since 2011, the 16R Threshold and Taxiway A1 have required annual replacement programs to remediate slabs at Sydney Airport. Antoun was engaged by SYD to demolish and install fourteen concrete slabs that
required immediate attention.

Location:

Sydney, NSW

Budget:

<$1m

Duration:

1 week

Sector:

Completed:

2018

The scope of works included

  • Initial works involved liaising with SYD (Sydney Airport) to disconnect services including AGL
  • Antoun saw cut the defective slabs the night before the demolition process
  • Once demolished, the slabs were anchor lifted and removed from the site along with other waste
  • The subgrade was compacted and prepared before the installation of dowels to the relevant specifications
  • Antoun places the new concrete pavements using Rapid Set (High Early Structural Strength Concrete) and produced a broom finish for the slabs

The Results

Antoun ensured that all works were completed by 4:45 am each morning to ensure SYD Operations Department were able to inspect the area prior to opening for aircraft traffic. There was no operation delay producing an efficient outcome for involved stakeholders.

Play Video

Contact us to find out how we can help

Learn more about
what we do

Relevant documents

Antoun NSW EMS certificate
2018-2021

RMS Prequalification letter &
Certificate expApr22.pdf

Antoun NSW EMS certificate
2018-2021

RMS Prequalification letter &
Certificate expApr22.pdf

Who we work with